Each of the following accurately describes total float in a schedule EXCEPT:
The amount of time that an activity can be delayed from its early start date without delaying project completion is called: Questions and Answers PDF 12/115
In its simplest form, what is the main drawback of critical path method scheduling?
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
You are retained by a contractor who asks you to perform a simple as -planned versus as -built analysis (APAB) of a large hydro -electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?