Question 31 🔥

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

Question 32 🔥

Each of the following accurately describes total float in a schedule EXCEPT:

Question 33 🔥

The amount of time that an activity can be delayed from its early start date without delaying project completion is called: Questions and Answers PDF 12/115

Question 34 🔥

In its simplest form, what is the main drawback of critical path method scheduling?

Question 35 🔥

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

Question 36 🔥

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?