Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Using the normal schedule, what is the early finish date and total float of Activity 10002?
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?