When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Choose two.)
In a joint trench using concrete, what is the MINIMUM vertical and horizontal separation between the electrical and the ICT distribution designer conduits?
Who prepares the submittals that are reviewed and approved to ensure that the client’s design criteria is met in regards to material selection?
Rolling objects create what type of load on an access flooring system?
What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?