A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?
During online, collaborative meeting sessions, a project team is consistently in consensus, which is causing a creativity roadblock. Which of the following can the facilitator do to minimize this issue?
During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?