An engineer needs to limit the power consumption of a chassis without powering down any server nodes.Which step should the engineer take to perform this task?
In VRTX the following features are enabled:1. Server Module Firmware Update2. Remote syslog3. iDRAC Single Sign-on.4. Server configuration5. Chassis grouping6. Enclosure level backupWhich license type is required?
An engineer is troubleshooting a blade server in an FX2s. The compute sled in SLOT 3 will NOT power on. The engineer has taken the server down to minimum to POST. The server still does NOT power on. The engineer then swaps sleds SLOT 2 and 3. The iDRAC initializes in SLOT 2 but SLOT 3 is stuck at initializing the iDRAC.What are two possible sources of the issue? (Choose two.)
A customer has five VRTXs in a chassis group that they need to disband. The engineer disbands the chassis group from the group leader, but a networking interruption prevents two of the VRTXs from getting the signal to leave the group.What should the engineer do to finish disbanding the chassis group?
An engineer has a new blade chassis that is full. The chassis has six power supplies. The chassis at peak power usage needs at minimum four power supplies.Redundancy is NOT a concern.The engineer needs a policy to meet the current needs and provide enough power to a fully populated chassis.Which policy should the engineer choose?
An engineer is installing two PCIe NICs into an existing VRTX chassis. Node 1 has three PCIe cards assigned to it already. After installation, the engineer is unable to assign the two new NICs to node 1.What should the engineer do to assign the two PCIe NICs to node 1?