You must implement high availability features in the design for a data center. Every network device in this part of the data center only has one routing engine.Which high availability feature should you use in this scenario?
You are asked to create an underlay network that will scale from a small system to a large system and can be integrated into a Contrail solution.In this scenario, which protocol satisfies these requirements?
You are designing a data center where all your servers in each rack will be connected to two top-of-rack (ToR) switches using Layer 2, as shown in the exhibit. You must implement a high availability solution that maintains link layer connectivity to each server when one of the ToR switches fails.In this scenario, which solution will accomplish this task?
You are implementing a new data center and need to plan to connect it to your existing data center. You have the requirement for active/active forwarding to enable load balancing and reduce failure times.Which two technologies should be evaluated for this design? (Choose two.)
Which three statements are correct regarding a Clos-style IP fabric network? (Choose three.)
You are inspecting a small data center your company just purchased. You notice several blank panels and cable management system components in a storage room that are not installed on the equipment racks.In this scenario, which two statements would you include in your inspection report? (Choose two.)