Your development team is using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template.The team has identified all of the acceptance criteria for a new application. This data currently resides in a series of spreadsheets.You need to enter the criteria into TFS for team traceability and tracking.Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
DRAG DROP -You have a list of tasks entered into Microsoft Visual Studio Team Foundation Server (TFS) 2012. Each task has an estimated effort and assigned to a team member.You have limited resources available. Due to external requirements, the start date and end date of the current iteration are fixed. Several of the tasks have dependencies on one another.You need to identify a critical path.What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)Select and Place:
Your development team uses Scrum as its process framework and utilizes the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template.Your product owner requests making an internal system public. The request is top priority for the next sprint.You need to determine if the team can commit to the request for the next sprint.What should you do?
Your development team is using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template.You identify the high business value requirements of a project.You need to prioritize the requirements and ensure that the updates are reflected on the TFS reports.Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You manage a geographically dispersed development team that uses the Microsoft Visual Studio Scrum 2.0 process template.Each of the four locations has approximately six team members.You need to optimize the teams performance to minimize the impact of the geographic dispersion.What should you do?
You are developing a release plan for a new project.You need to create a risk management plan.Which three activities or elements should you include in your plan? (Each correct answer presents a complete solution. Choose three.)