You are a project manager who uses Project Standard 2013.You manage a large project and are capturing actual work for the tasks as they are being worked.You do not need to enter the time on the actual day worked; however, you need to capture the total amount of time spent on the task.The fixed work task has a baseline of 20 hours, and the developer's timecard displays the following hours:✑ Monday = 2 hours✑ Tuesday = 8 hours✑ Wednesday = 4 hours✑ Thursday = 2 hours✑ Friday = 2 hoursThe developer informs you that the task is now complete.You need to update the actual work and mark the task complete.What should you do?
You are a project manager for a company that uses baselines in Project Standard 2013.Project stakeholders approve an update to the baseline of a project in progress. You enter the new tasks necessary to include the project schedule changes.You need to update the baseline for the new tasks.What should you do?
You manage a project schedule by using Project Professional 2013.You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00.You need to view graphically which tasks and resources are causing the $5,000.00 cost variance.What should you do?
While scheduling with Project Professional 2013 you notice that there are three days of remaining duration on the Database Design task.The resource performing this task indicates that the work is completed.You need to update the schedule to reflect this change.What should you do?
Your project managers manage several projects using Project Professional 2013. Each individual project contains a saved baseline.You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes.What should you do?
You manage a project by using Project Professional 2013.The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day.You need to solve this problem.What should you add to the task?