You are a project manager for a software development company that uses Project Professional 2013.For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes. Additionally, your company's status reports of project progress are based on Work and Cumulative Work.Thirty minutes before a meeting is scheduled to begin, the president of your company asks you to present the status report at the meeting.You need the report to show all project tasks, resources assigned, and their respective Work and Cumulative Work on a monthly basis.What should you do?
You are a project manager who uses Project Professional 2013.You manage a critical project, which involves many team members. You are the only team member who has Project Professional 2013. You need to receive updates from team members directly from Microsoft SharePoint without having to reenter the updates in your project.What should you do?
You are a Project Manager who uses Project Professional 2013.You manage a critical project, which is synchronized with a Microsoft SharePoint Task List.One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.What should you do?
DRAG DROP -You are an independent project manager who uses Project Professional 2013.You are starting a new marketing campaign project for your own company. You want to use Project Professional 2013 to plan and manage this project. You have never worked with a marketing project, so you choose to start your project plan with one of many templates available at the Microsoft Office website.You need to access the correct template.Which three actions should you perform in sequence? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)Select and Place:
DRAG DROP -You are an independent project manager who uses Project Professional 2013 and wants to extend the standard functionalities of it.You need to find and install an app from the Office Store.Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)Select and Place:
You are an independent project manager who uses Project Professional 2013.You work in multiple projects for different customers and use one project to manage all their tasks. You create a custom field called Customer Name to identify the customer, and you use the Cost field to monitor the amount of money for each task.You need to view the most expensive detail tasks in the top of your table without subtotals and summaries.You turned off summary tasks. What should you do next?