Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.A client subcontracts production work to a vendor for production operations.You need to model subcontracting of route operations in production orders.Solution: Ensure that the service product is stocked and is part of the Bill of Materials.Does the solution meet the goal?
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.This item has the following Lean setup:• The setup uses a Lean schedule group with a throughput ratio = 2.• The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.• The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).• The throughput is 10 per hour.You need to set up a Discrete operation to mirror the item’s production flow activity.What should you do?
A company uses Process manufacturing for most products and Discrete manufacturing for other products. The company is creating a formula for a new product. The new item will be used to make a name brand product and two generic brand products.This item has the following requirements:• Production of the name brand and generic products must use the same formula.• The company must produce all three items at the same time.You need to create a produced item that can make two generic items and one main item.How should you set up the item?
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.A manufacturing company produces electronic components and devices.The company has scheduling issues related to using working time calendars in manufacturing.You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.Solution: Disable route groups for a process job type.Does the solution meet the goal?
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.A manufacturing company produces electronic components and devices.The company has scheduling issues related to using working time calendars in manufacturing.You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.Solution: Enable route groups for a capacity job type.Does the solution meet the goal?
You are the lead product design engineer at a plastics manufacturing company.You implement a new process that uses a single tool to produce three finished goods at the same time.You need to set up the planning item number and formula to correctly to manufacture the three items.Which three actions should you perform? Each correct answer presents part of the solution.NOTE: Each correct selection is worth one point.