Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types.What setup is required to enable this kind of revenue recognition?
Where should you specify the Default Capitalized Interest Rate Schedule?
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement?
Your administrator creates maintenance conditions on the Maintain Project Enterprise Labor Resources page. An HCM person is included in a condition with a process order value of 1 and, additionally, there are three other conditions, all with a process order value of 10.Which two statements are correct about the Maintain Project Enterprise Labor Resources process as it relates to process order values? (Choose two.)
Your customer has the following setups on the project plan type that they are using for their projects:Use Task Planned Dates as Task Assignment Dates = YesAutomatically Roll Up Task Planned Dates = YesSynchronize Task Transaction Dates with Planned Dates = NoWith these setups in place, you perform the following actions:1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.2. Create another new subtask (Sub Task 2) after the previous action is saved.What would the correct behavior of the application be after these actions?
Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?