Question 37 🔥

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.The Stage Plan for stage 3 has been produced.The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.None of the ֲ£500 change budget has been used to date and this is available for the stage.Which 2 statements apply to the Plan prerequisites section?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 38 🔥

Which is a correctly defined acceptance criterion for the transferred facilities computer system?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 39 🔥

Which of the following statements is true of the business interest on the project?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 40 🔥

During stage 4, a work package was authorized for the 'delivered pilot courses' to be completed by the end of week 2. The 'finalized materials' work package will start in week 3. Both work packages have zero tolerances, and finalizing the materials is dependent on feedback from the pilot courses.During week 1, there were some problems with the pilot courses, so at the start of week 2 the team manager rescheduled the courses to week 3, and reported this in the weekly checkpoint report as the end of week 2.Should the team manager have reported this delay previously as an issue, and why?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 41 🔥

During the delivery of the initial pilot course, an issue was raised about the technology defined in the 'training venue specifications'. During project closure, the project manager confirmed that the issue was recorded in the issue log and an entry in the daily log recorded how it had been resolved for the remaining pilot courses. The project manager then produced a related lessons report.Is this an appropriate application of the 'learn from experience' principle, and why?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 42 🔥

Which 2 statements should be recorded under the Reasons heading?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question

Lorem ipsum dolor sit amet consectetur. Eget sed turpis aenean sit aenean. Integer at nam ullamcorper a.

© 2024 Exam Prepare, Inc. All Rights Reserved.