The time-box for a Daily Scrum is:
Which phrase best describes a Product Owner?
The length of a Sprint should be:
What is the Product Owner responsible for during the Sprint Retrospective? (Choose the best answer.)
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. TheDevelopment Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.A good way to continue is:
When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?