Listed below are some risks and issues that might be encountered during the course of a project. Identify which of the following are risks (not issues).A) After extensive training, marketing representatives might still not be ready to take orders after the project is launched.B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.C) Funding was not approved.D) Requirements, as currently defined, are unclear.
As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length of Sprint is determined keeping in mind the changes expected. Which of the following statements is true in this regard?
During a Retrospect Sprint Meeting, the Scrum team conducted an Explorer-Shopper-Vacationer-Prisoner exercise. One of the participants indicated that he feels like an Explorer. Which of the following best describes who an Explorer is?
The Scrum Master must ensure that a sustainable pace is maintained throughout every Sprint. What does sustainable pace mean in the context of Scrum?
A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?
The Chief Scrum Master facilitates the Scrum of Scrums Meeting. Which of the following statements about a Scrum of Scrums Meeting is true?