Answer the following questions about the tracking and control activities carried out within the project. Decide whether each activity has been applied appropriately and select the response that supports your decision. During Foundations, the key stakeholders had very different views about the content and prioritisation for the high -level requirements. As a result, the Project Manager organized a Facilitated Workshop with the project team to discuss and agree the requirements. Is this an appropriate application of Agile Project Management for this project?
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand -up meeting as a temporary Specialist team member, to represent any Planning Authority issues. Is this an appropriate application of Agile Project Management for this project? Questions PDF 46/157
During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what needed to be done before these would be acceptable. Is this an appropriate application of Agile Project Management for this project?
The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk - rounds of the new bedroom and en -suite bathroom facilities throughout the project. Is this an appropriate application of Agile Project Management for this project?
During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re- engage this group and explore discrepancies in understanding. Is this an appropriate application of Agile Project Management for this project?