Answer the following questions about the contents of the DSDM products. Each of the following questions includes true statements about the project but only two statements are appropriate entries for the DSDM product Questions PDF 49/157 identified. Remember to limit your answers to the number of selections requested in each question. Which 2 statements represent appropriate entries for the Business Case?
Which 2 statements represent appropriate entries for the Prioritised Requirements List?
Which 2 statements represent appropriate entries for the Development Approach Definition?
Which 2 statements represent appropriate entries for the plan for Post -Project activities?
Several of the web developers working on the project have no Agile experience. When answering the questions in the Project Approach Questionnaire (PAQ), the Project Manager could not agree with the statement 'all members of the project understand and accept the DSDM approach'. What action should the Project Manager take? Questions PDF 53/157
Time is running short and the Must Have requirements for the data entry screen of the web page, as recorded in the Prioritised Requirements List, are not going to be completed on time. What action should the Project Manager take?