Question 1 🔥

DRAG DROP -Your company uses Project Professional 2013.You are a program manager in charge of a multi-program software integration project. The project is scheduled from January 1, 2012-August 3, 2013. You have a consultant resource that charges a different rate based on each task completed. Tasks 1 through 9 are billed at a rate of $150.00 per hour. Tasks 10 through 20 are billed at a rate of $175.00 per hour.You need to set up your schedule to ensure that the correct resource rate is associated with the correct tasks.Which two actions should you perform in sequence? (To answer, move the appropriate two actions from the list of actions to the answer area and arrange them in the correct order.)Select and Place:

Question 2 🔥

Your organization uses Microsoft Project 2013.You are finalizing the Project Schedule for a very complex project with over 100 resources.You need to ensure that all tasks are assigned to resources.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 3 🔥

You are a project manager who uses Project Professional 2013.You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project.The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20.You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 4 🔥

You are a project manager for a software development company. You use Project Professional 2013.You manage an integration project, and you discover that you need to add additional resources to the integration tasks in order to meet your development complete milestone date. The project is behind schedule, so you must shorten the duration of the integration development work.You identify two additional resources to work on the integration task. When you add these resources, your task now shows it will complete three days ahead of schedule, which leaves a contingency window for issues that may arise.In order to shorten the duration of the task when the resources are added, you need to set the task type before adding the resources.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 5 🔥

You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 6 🔥

You are a program manager who uses Project Professional 2013.You manage a portfolio of projects for a large point of sale implementation. All of your project managers have created individual project schedules. You discover that you have resource constraints since multiple resources are working on multiple projects.You need visibility into resources across all projects so that you can most efficiently manage the resources and their availability.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question