You are a project manager for a company that is based in New York and London. The company uses Project Professional 2013.Teams from both offices are working together on a project. Since the two offices are located in different regions, the teams have separate company holiday schedules and working times.You need to ensure that the effort for each resource and task is set up properly in the calendar.You want to achieve this goal by using the least amount of time and effort.What should you do?
Your company uses Project Professional 2013.You have several projects that are part of a program, but you do not use Project Server. You use a Resource Pool file to share resources across all projects.You are informed that one of the projects is cancelled before it starts. As a result, you need to delete the project.What happens in the resource pool after you delete the project?
You are a project manager for a company that uses Project Professional 2013.You are developing a schedule and plan to use the leveling order of Priority, Standard.You need to create a task which leveling will not change.What should you do?
You are a project manager who uses Project Professional 2013.You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.You need to monitor this phase closely to ensure that it does not overrun.What should you do?
You are using Project Standard 2013.You want the ability to see only tasks that have finish dates past their deadline dateYou need to achieve this goal using a custom field.What should you do?
You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks, you get an error.You need to correctly assign the resource.What should you do?