You are using Project Standard 2013.Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details.You need to show one line item that displays all the requested information in the Gantt view.What should you do?
Your company uses Project Professional 2013.You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling and want to prioritize the projects so that Project 1 is the highest priority project and gets all the required resource availability first. Project 2 then gets resources as they become available from Project 1.You need to maintain this priority throughout the execution of the project.What should you do?
Your organization uses Project Professional 2013.You are setting up a preliminary schedule by using manually scheduled tasks.As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task.You need to determine the cause of the wavy red line.What should you do?
You are a project manager who uses Project Professional 2013. You have worked on a project for four years and have created a very detailed project plan inProject Professional 2013. You use milestones as key deliverables, and you use summary tasks as phases.Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one MicrosoftPowerPoint slide.You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.What should you do?
You are a project manager who uses Project Standard 2013.You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in yourMicrosoft SharePoint Intranet Environment. These documents are 25 megabytes in size.You need to share this project plan by email with your team and ensure that they can easily access the documents.What should you do?
You are a program manager who uses Project Professional 2013.You manage a portfolio of projects for a large point of sale implementation. All of your project managers have created individual project schedules. You discover that you have resource constraints since multiple resources are working on multiple projects.You need visibility into resources across all projects so that you can most efficiently manage the resources and their availability.What should you do?