Ready to Pass Your Certification Test

Ready to guarantee a pass on the certification that will elevate your career? Visit this page to explore our catalog and get the questions and answers you need to ace the test.

microsoft 74_343

Custom view settings

Exam contains 97 questions

Page 4 of 17
Question 19 🔥

You manage a project for an organization that relies heavily on schedule baselines in Project Standard 2013.A change is approved for an in-progress project which you manage. You enter the new tasks necessary to include the changes to the project schedule.You need to update the baseline in the most efficient manner.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 20 🔥

You manage a project by using Project Standard 2013.You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 21 🔥

You are a manager for an organization that uses Project Professional 2013.A critical project shows average finish variance values between 5-10 days for the tasks.You need to interpret these variance values to determine the next course of action to take.What do these variance values mean?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 22 🔥

You are a project manager who uses Project Professional 2013.When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values.You need to resolve the negative Total Slack values.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 23 🔥

You manage a project by using Project Professional 2013.A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.You need to implement a solution to meet the stakeholder's request.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question
Question 24 🔥

You are a program manager who uses Project Professional 2013.You manage a portfolio of projects for a large point of sale implementation. All of your project managers have created individual project schedules. You discover that you have resource constraints since multiple resources are working on multiple projects.You need visibility into resources across all projects so that you can most efficiently manage the resources and their availability.What should you do?

Which database solution meets these requirements?
Highly voted
Highly voted
Highly voted
Highly voted
Discussion of the question

Lorem ipsum dolor sit amet consectetur. Eget sed turpis aenean sit aenean. Integer at nam ullamcorper a.

© 2024 Exam Prepare, Inc. All Rights Reserved.